OCD Video Board Update End of Day Aug 18 (35% Complete)
Aug 18, 2022, 7:43 PM
Today the 18th it looks like roughly 180 panels were installed a mix of large and small so a very good day with an estimated total of 510 panels of 1,440 or 35% complete. At this rate it will require about 6 days to finish panels. Speed is growing every day.
I don't know if the long lead time installation item is the panelwork, but this would tell you that we might have a new board for 1st home game and most likely for LA Tech. At current rate panels would be near to 50% tomorrow.